19,531R Pcl Civil Constructors, Inc.

By: Cal-OSHA Decisions

Digest of COSHAB's Decision After Reconsideration dated March 4, 1999, Docket No. 93-R3D2-2373. James P. Gazdecki, Chairman; Bill Duplissea and Bryan E. Carver, Members

The Appeals Board affirmed the ALJ decision of September 7, 1994 [Digest 18,614], with respect to a willful/serious violation carrying a $37,500 penalty.

Employer was cited for the willful/serious violation in October of 1993; an ALJ affirmed the violation in September of 1994. Employer filed its petition for reconsideration in October 1994 and it was granted that November. Excavations, Protection from Cave-Ins (1541.1(a)(1))---Citation, Provided Sufficient Notice of the Violation---S

Read More...