PLASTERING CONTRACTOR
Digest of COSHAB-ALJ's decision dated February 24, 1978, Docket Nos. 77-R1D3-1153 and 1154. August F. Cetti, Administrative Law Judge.
For App: Julia Warda, President. For DIS: Vic F. Dayco, CSE.
Employer, Under the Act, Corporate Change of Management---Violation, Repeat.
A repeat/general violation of 1644(a)(6) and penalty of $135 were each affirmed.
"The uncontroverted evidence established that at the time of the current inspection the employees of John D. Warda, Inc., were working on a work platform 10 feet high that did not have a midrail or end rail. The evidence also established that Appellant corporation had been ci