Digest of COSHAB-ALJ's decision dated November 9, 1981, Docket Nos. 81-R1D3-529 and 530 (San Jose, CA). Adolf Loeb, Administrative Law Judge.
For Employer: Larry M. Willis, President. For DOSH: John L. Dailey, CSE.
This appeal was denied. A general violation of 1715(c)(1) (lifting plan for panel erection) was established.
Construction, Erection Plans, at Site. Employer was contracted to install concrete panels that were to be the walls of a building.
"Employer's president testified that a plan was in fact at the site the day the lifting began but as the rigging details were the same for all panels - R-12 - there was no need to keep the plan at th