16,994 M & M Construction

By: Cal-OSHA Decisions

Digest of COSHAB-ALJ's decision dated February 5, 1987, Docket Nos. 86-R2D5-1107 thru 1109 and 1293 thru 1295 (Clovis, CA). Ronald F. Peters, Administrative Law Judge.

For Employer: William Massey, Partner. For DOSH: Robert Larsen, CSE.

Of five contested additional penalties for failure to abate, two were affirmed, one was vacated, and two were reduced; a total of $1,445 in contested penalties was reduced to $145. The violations (which were admitted) and disposition of the proposed penalties:

1510(e) (safety Instructions for employees). A $15 further penalty was affirmed, for failure to have a code of safe practices. (This and other proposed additi